At yesterday's kick-off meeting of the "Biogas Trebsen" project, the responsible project participants met to co-ordinate the launch of the project's construction phase.
Mr. Phillip Bussmann, project engineer at revis bioenergy GmbH, was very satisfied: " we are ahead of schedule, so that construction can start in spring 2018 and commissioning in November 2018. We look forward to expanding our portfolio of 100% biomethane from waste materials with this project. "
With this project, revis bioenergy GmbH will take over the produced raw biogas and upgrade it into biomethane with their long proven technology. For this purpose, revis is building one of its 550 Nm³ / h upgrading plants to feeding the high-quality biomethane into the grid.