Exemplary Biogas and Biomethane Plants
High quality for a flawless operation

The materials we use have proven their reliability and resilience for years already. A further special feature which characterizes our biogas and biomethane plants is the possibility to process a large number of varied raw and residual substances.

Biogas plant BWM Dülmen

Plant characteristics:

  • Biogas plants with 1400 Nm3/h biogas 
  • Biogas upgrading plant with 700 Nm³/h biomethan
  • Planning, plant construction, gas processing as well as operation of biogas by revis bioenergy
  • Processing of approx. 65,000 t of solid manure
  • Construction time: 6 months
  • Operation of the plant since spring 2020

Biogas plant Trebsen

Plant characteristics:

  • Biogas upgrading plant with 550 Nm³/h biomethan
  • Upgrading of the biogas from the anaerobic process water treatment of a paper mill
  • Planning, plant construction, gas processing as well as operation of biogas by revis bioenergy
  • Construction time 6 months
  • Operation of plant since September 2018

Biogas plant + biomethane plant Gommern

Plant characteristics:

  • Biogas plant 1 with 1400 Nm3/h biogas
  • Biogas plant 1 with 700 Nm3/h biomethane
  • Planning, plant construction, gas processing as well as operation of biogas by revis bioenergy
  • Processing of approx. 50,000 t silage per year
  • Capacity of silo system approx. 6,500 m2 sufficient for approx. 30,000 t (85% of the annual requirement)
  • Biomass approx. 50,000 t renewable raw materials (maize, millet, grass, whole crop silage) from approx. 10 suppliers
  • Construction time 6 months
  • Operation of plant 1 since 4 May 2017
  • Operation of plant 2 end of 2018

Biogas plant + biomethane plant I+II Oebisfelde

Plant characteristics:

  • 2 biogas plants each with 1400 Nm3/h biogas
  • Planning, plant construction, gas processing as well as operation (up until 2016) by revis bioenergy
  • Processing of approx. 55,000 t silage per year
  • Capacity of silo system approx. 15,000 m2 sufficient for approx. 48,000 t (85% of the annual requirement)
  • Biomass approx. 55,000 t renewable raw materials (maize, millet, grass, whole crop silage) from approx. 10 suppliers
  • Construction time 6 months
  • Operation of plant 1 June 2013
  • Operation of plant 2 June 2014
  • Project sold

Biogas plant + biomethane plant I+II Satuelle

Plant characteristics:

  • 2 biogas plants each with 1400 Nm3/h biogas
  • Planning, plant construction, gas processing as well as operation (up until 2016) by revis bioenergy
  • Processing of approx. 55,000 t silage per year
  • Capacity of silo system approx. 15,000 m2 sufficient for approx. 48,000 t (85% of the annual requirement)
  • Biomass approx. 55,000 t renewable raw materials (maize, millet, grass, whole crop silage) from approx. 10 suppliers
  • Construction time 6 months
  • Operation of biogas / biomethane plant 1 June 2013
  • Operation of biogas / biomethane plant 2 June 2014
  • Project sold

Biogas plant + biomethane plant Uchte

Plant characteristics:

  • Biogas plants with 1400 Nm3/h biogas 
  • Planning, plant construction, biogas-biomethane processing by revis bioenergy on behalf of an external client
  • Biomass approx. 35,000 t renewable raw materials
  • Capacity of silo system sufficient for approx. 50,000 t (140% of the annual requirement– 35,000t)
  • Container height approx. 17 m
  • Construction time 6 months
  • Commissioning of the biogas plant and the biomethane plant 2011

Trelder Berg Energy Park

Plant characteristics:

  • 3 biogas plants with a total of 8 MW el. power
  • Planning, construction, funding and operation by revis bioenergy
  • Processing of approx. 85,000 t silage per year
  • Approx. 75 farmers as suppliers
  • Heat supply of the neighbouring wood pellet production
  • Construction time 6 months
  • In operation since the end of 2006
  • Project sold

 

 

Film "Construction of a biogas-biomethane plant" by revis bioenergy GmbH

Film Construction of a biogas-biomethane plant by revis bioenergy GmbH></a></p></div>


							</div>
						</div>

					

			</div>
		</div>
	</section>

	<footer>
		<div class=


address

revis bioenergy GmbH
Lippstädter Straße 42
48155 Münster

contact

phone: +49 251 - 609845-0
fax: +49 251 - 609845-22
info@revis-bioenergy.de